When preparing a company’s flexible budget, which manufacturing cost(s) will change as the volume increases or decreases? (You may select more than one answer. Single click the box with a check mark for correct answers and double click to empty the box for the wrong answers.)
Which manufacturing cost(s) will not change as the volume changes? (You may select more than one answer. Single click the box with a check mark for correct answers and double click to empty the box for the wrong answers.)
Explanation / Answer
Will change: Variable Manufacturing Overhead Direct Materials Direct Labor Will not change: Fixed Manufacturing Overhead Depreciation