[ The following information applies to the questions displayed below. ] rev: 10_
ID: 2521420 • Letter: #
Question
[The following information applies to the questions displayed below.]
rev: 10_29_2012
38.
Assume that the company computes variances at the earliest point in time. The direct-labor efficiency variance is:
$8,002F.
$8,002U.
$9,120F.
$9,120U.
None of these.
39.
Assume that the company computes variances at the earliest point in time. The standard hours allowed for the work performed are:
rev: 10_25_2011
40,090.
39,150.
39,000.
38,900.
None of these.
Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.60 per pound $7.80 Direct labor 6 hours at $7.60 per hour 45.60 Actual results: Units produced 6,500 units Direct material purchased 26,100 pounds at $2.80 $73,080 Direct material used 19,200 pounds at $2.80 53,760 Direct labor 40,200 hours at $7.40 297,480Explanation / Answer
Q38 $9,120F. Q39 39,000 Hours Dear Student Thank you for using Chegg Please find below the answer Statementshowing Computations Paticulars Amount Standard hour per unit 6.00 Actual No of Unit 6,500.00 Q39 Standard hours allowed = 6500 *6 39,000.00 DLEV = (SH-AH)SR DLEV = (39000 - 40,200)7.60 DLEV = 9,120 U
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.