Curtiss Construction Company, Inc., entered into a fixed-price contract with Axe

ID: 2525697 • Letter: C

Question

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows At 12-31-2018 At 12-31-2019 At 12-31-2020 100% Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date 10% 60% 410,000 3,270,000 900,000 $5,102,000 $2,980,000 2,060,000 2,410,000 4,720,000 Required 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs

Explanation / Answer

1. Completed contract method:

2018 : No profit or loss recognized

Percentage completion method:

Year 2019 Contract Price 4,720,000 Estimated Costs 5,040,000 Loss recognized -320,000
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote