Required information [The following information applies to the questions display

ID: 2533526 • Letter: R

Question

Required information [The following information applies to the questions displayed belowj Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. $6.00 per Ib.) Direct labor (1.7 hrs. $10.00 per hr.) Overhead (1.7 hrs. $18.50 per hr.) Total standard cost $24.00 17.00 31.45 $72.45 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the 75% capacity level. Overhead Budget (75% Capacity Variable overhead costs Indirect materials Indirect labor Power Repairs and maintenance Total variable overhead costs $ 15,000 75,000 15,000 30,000 $135,000 Fixed overhead costs Depreciation-Building Depreciation-Machinery Taxes and Supervision Total fixed overhead costs 24,000 71,000 16,000 225,750 insurance Total overhead costs $471,750 The company incurred the following actual costs when it operated at 75% of capacity in October. Direct materials (61,000 Ibs. @ $6.10 per lb.) Direct labor (19,000 hrs.$10.40 per hr.) Overhead costs $ 372,100 197,600 Indirect materials Indirect labor Power Repairs and maintenance Depreciation-Building Depreciation-Machinery Taxes and insurance Supervision $ 41,700o 176,100 17,250 34,500 24,000 95,850 14,400 225,750 629,550 $1,199,250 Total costs

Explanation / Answer

units produced = 20000*75% = 15,000 Actual cost Standard cost AQ * AP AQ * SP SQ * SP 61,000 * 6.1 61,000 * 6 60000 * 6 372100 366000 360000 6100 6000 Direct material price variance 6100 U Direct material Quantity variance 6000 U total direct materials variance 12100 U Actual cost Standard cost AH * AP AH * SP SH * SP 19,000 * 10.4 19,000 * 10 25500 * 10 197600 190000 255000 7600 65000 Direct labor rate variance 7600 U Direct material Efficiency variance 65000 F total direct labor variance 57400 F

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote