Chirico Manufacturing Company uses job costing system. The following job cost re

ID: 2533683 • Letter: C

Question

Chirico Manufacturing Company uses job costing system. The following job cost records were provided for January, the company’s first month of operations: Job 1 Job 2 Job 3 Job 4 Job 5 Direct materials used $100 $400 $300 $200 $400 Direct labor cost 300 600 200 500 100 Allocated overhead 300 600 200 500 100 Total $700 $1,600 $700 $1,200 $600 Date started 01/02 01/10 01/20 01/25 01/22 Date completed 01/18 01/20 01/30 02/02 02/10 Date delivered to customer 01/20 01/25 02/02 02/05 02/15 There was no inventory of any kind at the beginning of January. 3. The amount of cost of goods manufactured for January is A) $2,300. B) $1,800. C) $4,800. D) $3,000. 4. The amount of cost of goods sold for January is A) $4,800. B) $2,300. C) $3,000. D) $1,800. 5. The amount of ending work in process as of January 31st is A) $3,000. B) $1,800. C) $2,300. D) $4,800.

Explanation / Answer

Jobs 1 2 3 4 5 Direct materials used $100.00 $400.00 $300.00 $200.00 $400.00 Direct labor cost $300.00 $600.00 $200.00 $500.00 $100.00 Allocated Overhead $300.00 $600.00 $200.00 $500.00 $100.00 Total Cost $700.00 $1,600.00 $700.00 $1,200.00 $600.00 Date Completed 01/18 01/20 01/30 02/02 02/10 Date delivered to customer 01/20 01/25 02/02 02/05 02/15 Job Status COGM COGM COGM Job Status COGS COGS Job Status WIP WIP Cost of goods manufactured = Job 1 + Job 2 + Job 3 = $700+$1600+$700 = $3000 The answer is Option D. Cost of goods sold = Job 1 + Job 2 = $700 + $1600 = $2300 The answer is Option B. Ending work in process = Job 4 + Job 5 = $1200 + $600 = $1800 The answer is Option B.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote