Help with part B please SmartWatch Ltd. manufacture electronic security products
ID: 2547680 • Letter: H
Question
Help with part B please
SmartWatch Ltd. manufacture electronic security products. One such product is a tracking component used in building management systems. They manufacture two versions of the product, one for the general commercial sector (ref GCS) and a more robust version for Government use (ref GOV). While both products are manufactured in the same production cells using similar technology, there are differences in the manufacturing processes which utilise usage, and product quality tests. You are provided with the following information: varying levels of direct labour, plating bath Item Model GCS Model GOV 800 31 10 per week Total V.C. Direct Labour Minutes Unit Plating Bath Minutes/Unit QC Tests/ Unit 27 The total direct overheads per week in the production cell is made up of () plating bath costs of 10,800, and (i) QC Test costs of 8,400 The Accountant at SmartWatch insists on having the cost of these overheads absorbed into the product cost in proportion to the direct labour time used in each product; (i.e. traditional "absorption" costing approach). However, there is disquiet in the sales department that the company appears non-competitive in the important Government contract sector, and questions the validity of the company's costings for the GOV product. As Production Engineer at SmartWatch, you have been tasked by the Managing Director to report to him on the costing of these two products using the tradition absorption costing approach, (ABC) approach. and comparing ng these with the Activity Based C Required: A. Analyse the data above relevant to the alternative 'absorption' and ABC methods of applying the two overhead costs to the products. B. Using your results from above, write a report for the Managing Director making a case for the costing method you feel is more appropriate and why;- illustrating your comments by showing the impact of each method on the imputed total cost of each product.Explanation / Answer
A Model GCS Model GOV Total A Output Per week 2000 800 B Varibale Cost Per Unit 27 31 C Direct Labour Minutes Per Unit 6 10 D Plating Bath Minutes per unit 3 4 E QC Test per unit 4 5 F Total Labour Minutes 12000 8000 20000 G Plating Bath Cost apportioned on the basis of F 6480 4320 10800 H QC Test Cost apportioned on the basis of F 5040 3360 8400 I Total Plating Minutes (D*A) 6000 3200 9200 J Total QC Test Minutes (E*A) 8000 4000 12000 K Plating Cost Per Unit as per ABC (G Total/I Total)*D 3.52 4.70 L QC Test Cost as per ABC (H Total/J Total)*E 2.8 3.5 IF absorption Costing Follows Model GCS Model GOV Total 1 Variable Cost 27 31 2 Plating Cost P U ( G of above/A) 3.24 5.4 3 QC Test Cost P U ( H of above/A) 2.52 4.2 4 Total Cost 32.76 40.6 IF ABC Costing Follows Model GCS Model GOV Total 1 Variable Cost 27 31 2 Plating Cost P U (K) 3.52 4.70 3 QC Test Cost P U (L) 2.80 3.50 4 Total Cost 33.32 39.20 B. ABC is Appropriate method to be use than traditional abosorption method which uses labour hours as a base. Because absorption costing does not consider appropriate basis for each cost. As you can see In absorption method plating cost is spread over higher Labour minutes in Model GCS and hence Model GCS having Lower Cost as compared to Model GOV. also see vice a versa Effect on Model GOV.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.