Hi and thank you, I\'ve already completed reuirment 1 but need assistance on the
ID: 2550610 • Letter: H
Question
Hi and thank you, I've already completed reuirment 1 but need assistance on the rest.
3. Expected usage and costs for manufacturing overhead Skath Industries manufactures a variety of custom products. The company has traditionally used a plantwide activities for the upcoming year are as follows manufacturing overhead rate based on machine hours to Click the icon to view the expected usage and costs.) allocate manufacturing overhead to its products. The company estimates that it will incur $860,000 in total manufacturing overhead costs in the upcoming year and will 3(Click the icon to view the usage for Job 354) use 10,000 machine hours Click the icon to view the additional information about the hazardous waste disposal fees.) During the year, Job 354 is started and completed. Usage for this job follows: Read the requirements Requirement 1. Calculate the cost of Job 354 using the traditional plantwide manufacturing overhead rate based on machine hours Begin by calculating the plantwide overhead rate. First identify the formula used to compute the plantwide overhead rate then compute the rate. (Abbreviations used: MOHmanufacturing overhead, mfgmanufacturing) Total estimated manufacturing costs I Estimated total machine hours - Plantwide mfg. overhead rate 860,000 10,000 86 Calculate the cost of Job 354 Job Cost Record JOB 354 Direct materials Direct labor Manufacturing overhead allocated Total job cost Requirement 2. Calculate the cost of Job 354 using activity-based costing Manufacturing Costs 6,800 1,050 8,600 16,450 Begin by calculating the allocation rate for each activity. First determine the formula to compute the allocation rate in an activity-based costing system, then compute the rate for each activity. (Abbreviations used: est = estimated, MH-machine hours, Mach.-Machine, Eng.-Engineering) Activity cost allocation rate Mach. maintenance Eng. change orders Waste disposal per MH per order per poundExplanation / Answer
Requirement 2
Activity Based Costing
Formula
Total Estimated Activity Cost Pool
/
Total est. activity allocation base
=
Activity Cost Allocation Rate
Machine Maintenance
$ 200,000
/
10000
=
$ 20
per MH
Engineering Change Orders
$ 240,000
/
6000
=
$ 40
per order
Hazardous waste Disposal
$ 420,000
/
1500
=
$ 280
per pound
Job Cost Record
JOB 354
Manufacturing Costs
Maintenance Costs
$ 2,000
=100*20
Engineering Costs
$ 160
=4*40
waste Disposal costs
$ 2,2400
=80*280
Total Job Cost
$ 24,560
Requirement 3
The cost estimate based on the
activity-based costing rates
would provide more useful information because this cost estimate takes into account
the specific resources used by each product
This information can be used to
price jobs based on more accurate costs
Requirement 2
Activity Based Costing
Formula
Total Estimated Activity Cost Pool
/
Total est. activity allocation base
=
Activity Cost Allocation Rate
Machine Maintenance
$ 200,000
/
10000
=
$ 20
per MH
Engineering Change Orders
$ 240,000
/
6000
=
$ 40
per order
Hazardous waste Disposal
$ 420,000
/
1500
=
$ 280
per pound
Job Cost Record
JOB 354
Manufacturing Costs
Maintenance Costs
$ 2,000
=100*20
Engineering Costs
$ 160
=4*40
waste Disposal costs
$ 2,2400
=80*280
Total Job Cost
$ 24,560
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.