Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

On February 1, 2018, Arrow Construction Company entered into a three-year constr

ID: 2551258 • Letter: O

Question

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.000,000. During 2018, costs of S2,000,000 were incurred with estimated costs of s4.000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2.250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were s2.750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of $3,800,000 were incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over ü e time: loss$ on te project according to percentage of completion

Explanation / Answer

Solution:

2018

2019

2020

Contract price

8,000,000

8,000,000

8,000,000

Actual costs to date

2,000,000

4,500,000

8,300,000

Estimated costs to complete

4,000,000

3,600,000

0

Total estimated costs

6,000,000

8,100,000

8,300,000

Estimated total gross profit (loss)

2,000,000

100,000

-300,000

% of completion : 2/(2+4) = 1/3; (2+2.5)/(2+2.5+3.6) = .555

Gross profit (loss) recognition:

2018: 33.3333% * $2,000,000 = $666,667

2019: $-100,000 - 666,667 = - $766,667

2020 $300,000 - $100,000 = $200,000

2018

2019

2020

Contract price

8,000,000

8,000,000

8,000,000

Actual costs to date

2,000,000

4,500,000

8,300,000

Estimated costs to complete

4,000,000

3,600,000

0

Total estimated costs

6,000,000

8,100,000

8,300,000

Estimated total gross profit (loss)

2,000,000

100,000

-300,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote