Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

mpany makes two products-titanium Hubs and Sprockets. Data regarding the two pro

ID: 2566221 • Letter: M

Question

mpany makes two products-titanium Hubs and Sprockets. Data regarding the two products follow Labor- Hours Annual per Unit 0.80 17,000 units 0.40 54,000 units Hubs Sprockets Additional information about the company follows: a. Hubs require $27 in direct materials per unit, and Sprockets require $13. b. The direct labor wage rate is $16 per hour. c. Hubs require special equipment and are more complex to manufacture than Sprockets d. The ABC system has the following activity cost pools: erences tivity Overhead 25,200 140 $126,000 3,600 $208,000NA 252 0 3,600o special processing (machine-hours) General factory (organization-sustaining) Required 1. Compute the activity rate for each activity cost pool. 2. Determine the unit product cost of each product according to the ABC system. Complete this question by entering your answers in the tabs below

Explanation / Answer

ABC costing is a technique in which a company finds activity and assign the cost of each activity with resources of all products and services according to actual consumption by each.

1.Calculation of Predetermined overhead allocation rate.

Total cost

Allocation Base

Predetermined overhead allocation rate

Machine setups

25200

252

100*

Per setup

Special processing

126000

3600

35*

Per machine hrs.

Formula

*Total Cost/Allocation Base

2.

Calculation of overhead assigned between two products:

Hubs:

Activity cost pool

Activity rate (a)

Expected activity

(b)

ABC cost

(a)×(b)= (c)

Machine setups

$100 per setup

140 setups

$14,000

Special processing

$35 per M.hour

3600 M.hours

$126,000

Total ABC cost

$140000

Hence, the calculated total ABC cost is 140000.

Sprockets:

Activity cost pool

Activity rate (a)

Expected activity

(b)

ABC cost

(a)×(b)= (c)

Machine setups

$100 per setup

112 setups

$11200

Special processing

$35 per M.hour

0

0

Total ABC cost

$11200

Hence, the calculated total ABC cost is $11200.

Particulars

Hubs

Sprockets

Direct materials

27

13

Direct Labor

16*0.80=12.8

16*.40=6.4

Overhead

140000/17000 units=8.23

11200/54000=.20

Unit Cost

48.03

19.6

Total cost

Allocation Base

Predetermined overhead allocation rate

Machine setups

25200

252

100*

Per setup

Special processing

126000

3600

35*

Per machine hrs.