Question 7 1 points Save Answe Zanny Electronics Corporation uses a standard cos
ID: 2572531 • Letter: Q
Question
Question 7 1 points Save Answe Zanny Electronics Corporation uses a standard cost systerm for the production of its water ski radios. The direct labor standard for each radio is 0.9 hours. The standard drect labor cost per hou is $7.20. During the month of August, Zanny's water ski radio production used 6,800 direct labor-hours at a total direct labor cost of $48,708. This resulted in production of 6.900 water si radios for August. What is Zanny's labor rate variance for August? 9972 Favorable $1,188 Unfavorable S2.160 Favorable $2.808 UnfavorableExplanation / Answer
Labor rate variance = 48708-(6600*7.2)= 1188 Unfavorable Option 2 is correct
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.