> a) Moving to another question will save this response. Question 24 Two alternatives, code-named X and Y are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below lternative Alternative Materials costs Processing costs Equiprent rental $41,e80 $45,809 $17,800 516,888 $45,000 $17,86e $24 , 098 What is the financial advantage (disadvantage) of Alternative Y over Alternative X? O $132,000 O $119,000 O $145,000 $26,000 > Moving to another question wil savetnis response Type here to searchExplanation / Answer
Total cost of Alternative X = 41000+45000+17000+16000 = 119000
Total cost of Alternative Y = 59000+45000+17000+24000 = 145000
if we chose the alternative Y over Alternative X
disadvantage of chosing alternative Y is 26000(145000-119000)
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.