Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $6,200 for direct materials, $8,500 for direct labor, and $6,035 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $4,300 for direct materials and $4,600 for direct labor. Required 1a. Should any overhead cost be applied to Job W at year-end? Yes No 1b. How much overhead cost should be applied to Job W? Overhead costExplanation / Answer
1a. YES the overhead cost should allocate to Job W as well.
1b.the overhead cost allocated to job W is on the based of Direct labour
so the Job W overhead cost = $6,035/($8,500+$4,600)*$4,600=$2,119.16
2.The Job W cost will be reported at Work in process in the sigma corporation financial statments at the end of the year.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.