A company estimates that its required rate of return is 16 percent. Which of the
ID: 2633473 • Letter: A
Question
A company estimates that its required rate of return is 16 percent. Which of the following projects should the company accept, if all these projects are independent?
:
Project A requires an initial investment of $2,000,000 and generates a NPV of $58.
Project B has an IRR of 15.5 percent.
Project C requires an initial investment of $1,000,000 and generates an IRR of 16 percent.
None of the above.
Project A requires an initial investment of $2,000,000 and generates a NPV of $58.
Project B has an IRR of 15.5 percent.
Project C requires an initial investment of $1,000,000 and generates an IRR of 16 percent.
None of the above.
Explanation / Answer
Project A requires an initial investment of $2,000,000 and generates a NPV of $58.
Explanation: The project has a positive NPV while in other cases IRR is either less or equal to required rate of return. We must choose the project with a higher NPV should be chosen because there is an inherent reinvestment assumption
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.