Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A company estimates that its required rate of return is 16 percent. Which of the

ID: 2633473 • Letter: A

Question

A company estimates that its required rate of return is 16 percent. Which of the following projects should the company accept, if all these projects are independent?

:

Project A requires an initial investment of $2,000,000 and generates a NPV of $58.

Project B has an IRR of 15.5 percent.

Project C requires an initial investment of $1,000,000 and generates an IRR of 16 percent.

None of the above.

Project A requires an initial investment of $2,000,000 and generates a NPV of $58.

Project B has an IRR of 15.5 percent.

Project C requires an initial investment of $1,000,000 and generates an IRR of 16 percent.

None of the above.

Explanation / Answer

Project A requires an initial investment of $2,000,000 and generates a NPV of $58.

Explanation: The project has a positive NPV while in other cases IRR is either less or equal to required rate of return. We must choose the project with a higher NPV should be chosen because there is an inherent reinvestment assumption

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote