A firm is reviewing a project with labor cost of $6.80 per unit, raw materials c
ID: 2635406 • Letter: A
Question
A firm is reviewing a project with labor cost of $6.80 per unit, raw materials cost of $23.05 a unit, and fixed costs of $14,000 a month. Sales are projected at 8,800 units over the 3-month life of the project. What are the total variable costs of the project?
A firm is reviewing a project with labor cost of $6.80 per unit, raw materials cost of $23.05 a unit, and fixed costs of $14,000 a month. Sales are projected at 8,800 units over the 3-month life of the project. What are the total variable costs of the project?
Explanation / Answer
Total variable cost = Total amoun spent on labor ($6.80 per unit * 8,800 units) + Total amount spent on raw material ($23.05 per unit * 8,800 units) = $262,680.
Hope my solution solves your query.
Regards.