QUESTION 1 The IRR is a rate of return at which the NPV is equal to zero. True F
ID: 2649817 • Letter: Q
Question
QUESTION 1
The IRR is a rate of return at which the NPV is equal to zero.
True
False
5 points
QUESTION 2
IRR provides information about a project's safety margin.
True
False
5 points
QUESTION 3
Consider the following two projects.
Project A: IRR=15%, Cost of capital = 12%
Project B: IRR=18%, Cost of capital=20%
Project B should be chosen.
True
False
5 points
QUESTION 4
Stategic business plan is a short-run plan that outlines in broad terms the firm's basic strategy for the next year.
True
False
5 points
QUESTION 5
The discounted payback ignores cash flows beyond the payback year.
True
False
5 points
QUESTION 6
The MIRR method assumes that cash flows can be reinvested at the project's IRR.
True
False
5 points
QUESTION 7
If a project has nonnormal cash flows, the project might have multiple IRRs.
True
False
5 points
QUESTION 8
A project that costs $100 is expected to generate $120 next year. Its IRR is 20%.
True
False
5 points
QUESTION 9
Consider the following two mutually exclusive projects.
Project A: IRR = 20%, NPV = $100 million
Project B: IRR = 15%, NPV = $150 million
In terms of the firm's primary goal, Project A should be chosen.
True
False
5 points
QUESTION 10
NPV and IRR can produce conflicting conclusion when a choice is being made between mutually exclusive projects.
True
False
5 points
QUESTION 11
The net present value method assumes that all cash flows should be discounted at the project's IRR.
True
False
5 points
QUESTION 12
Two projects have the same NPV at their crossover rate.
True
False
5 points
QUESTION 13
The NPV profile shows the relationship between the NPV and the IRR.
True
False
5 points
QUESTION 14
If Project A's IRR is greater than Project B's IRR, Project A's NPV must be greater than Project B's NPV.
True
False
5 points
QUESTION 15
The payback method provides information about the project's liquidity and risk.
True
False
5 points
QUESTION 16
A project that costs $100 is expected to produce $50 per year for 5 years. The project's payback period is 2 years.
True
False
5 points
QUESTION 17
The reinvestment assumption built into the NPV is more reasonable than the reinvestment assumption built into the IRR.
True
False
5 points
QUESTION 18
The payback method ignores the time value of money whereas the discounted payback method consider the time value of money.
True
False
5 points
QUESTION 19
Project A and Project B have $10 million NPV and $5 million NPV respectively. If they are independent projects, only Project A should be chosen.
True
False
5 points
QUESTION 20
A project's MIRR is positive, it should be acceptable.
True
False
5 points
Explanation / Answer
1) True
2) True
3) False project A should be chosen
4) False
5) False
6) True
7) False
8) False
9) False
10) True
11) False
12) True
13) False
14) True
15) True
16) True
17) False
18) True
19) True
20) True
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.