Your task is to analyze two mutually exclusive projects: Year Cash Flow Project
ID: 2651376 • Letter: Y
Question
Your task is to analyze two mutually exclusive projects:
Year Cash Flow Project X Cash Flow Project Z
-0- -400,000 -50,000
1 25,000 20,000
2 60,000 15,000
3 60,000 20,000
4 540,000 20,000
Whichever project you chose, if any, you require a 15% return on your investment.
A] Using the payback criterion, which investment should you chose? Why?
B] Using the discounted payback criterion, which investment should you chose? Why?
C] Using the NPV criterion, which investment should you chose? Why?
D] Using the IRR criterion, which investment should you chose? Why?
E] Using the profitability index criterion, which investment should you chose? Why?
F] Based on your analysis in (A) thru (E), which investment should you finally chose? Why?
Explanation / Answer
A] Using the payback criterion, explain which investment should you chose?
Payback of Project X = 3 + 255000/540000
Payback of Project X = 3.47 Years
Payback of Project Y = 2+ 15000/20000
Payback of Project Y = 2.75 Years
Decision : Investment in Project Y Should be choosen
Working
B] Using the discounted payback criterion, explain which investment should you chose?
Discounted Payback of Project X = 3 + 293441/308747
Discounted Payback of Project X = 3.95 Years
Discounted Payback of Project Y = 3 + 8116/11435
Discounted Payback of Project Y = 3.71 Years
Decision : Investment in Project Y Should be choosen
Working
C] Using the NPV criterion, explain which investment should you chose?
NPV of Project X = 15305.48
NPV of Project Y = 3318.85
Decision : Investment in Project X Should be choosen
Working
D] Using the IRR criterion, explain which investment should you chose?
IRR of Project X = 16.23%
IRR of Project Y = 18.21%
Decision : Investment in Project X Should be choosen
Working
E] Using the profitability index criterion, explain which investment should you chose?
profitability index of Project X =(1+ NPV/Initial Investment)
profitability index of Project X = (1+15305.48/400000)
profitability index of Project X = 1.04
profitability index of Project Y =(1+ NPV/Initial Investment)
profitability index of Project Y = (1+3318.85/50000)
profitability index of Project Y = 1.07
Decision : Investment in Project Y Should be choosen
F] Based on your analysis in (A) thru (E), explain which investment should you finally chose?
Decision : Investment in Project Y Should be choosen as its IRR is higher than Project X
Year Cash Flow Project X Cumulative Cash Flow Project Z Cumulative -0- -400,000 -400,000 -50000 -50,000 1 25,000 -375,000 20000 -30,000 2 60,000 -315,000 15000 -15,000 3 60,000 -255,000 20000 5,000 4 540,000 285,000 20000 25,000Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.