What is the IRR for each of these projects? (Do not round intermediate calculati
ID: 2653648 • Letter: W
Question
What is the IRR for each of these projects? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))
Using the IRR decision rule, which project should the company accept?
If the required return is 12 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))
At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Garage, Inc., has identified the following two mutually exclusive projects:
Explanation / Answer
a1.
a-2. company should accept project B
a-3. Yes
NPV=4240.45
b-2. as per NPV decision rule project B should be selected because it is giving the higher NPV
A 0 1 -29100 -29100 1 0.909 14,500 13180.5 2 0.826 12,400 10242.4 3 0.751 9,250 6946.75 4 0.683 5,150 3517.45 cash inflow=33887 NPV=4787 0 1 -29100 -29100 1 0.833 14,500 12078.5 2 0.694 12,400 8605.6 3 0.578 9,250 5346.5 4 0.482 5,150 2482.3 cash inflow=28512 NPV=(588) IRR=lower discount rate+ lower rate NPV/Lower rate NPV-Highier rate NPV * difference in discount rate 10+4787/4787+588*10 18.90% B 0 1 -29100 -29100 1 0.909 4,350 3954.15 2 0.826 9,850 8136.1 3 0.751 15,300 11490.3 4 0.683 16,900 11542.7 cash inflow=35123.25 NPV=6023.25 0 1 -29100 -29100 1 0.833 4,350 3623.55 2 0.694 9,850 6835.9 3 0.578 15,300 8843.4 4 0.482 16,900 8145.8 cash inflow=27448.68 NPV=(1651.32) IRR=lower discount rate+ lower rate NPV/Lower rate NPV-Highier rate NPV * difference in discount rate 10+6023.25/6023.25+1651.32*10 17.84%a-2. company should accept project B
a-3. Yes
NPV=4240.45
b-2. as per NPV decision rule project B should be selected because it is giving the higher NPV
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.