This question is a variant of the Sport Hotel example that was presented in clas
ID: 2657077 • Letter: T
Question
This question is a variant of the Sport Hotel example that was presented in class, in the class notes, and in the Real Option chapter.
The change to consider is this: suppose that the value of the hotel is one of two values: $9.2 million if the city is successful in obtaining the franchise (and not $8 million as in the original problem) or $3.8 if the city is not successful in obtaining the franchise (and not $2 million as in the original problem). All other aspects of the problem are the same as originally presented. Incorporating these new values, and the real option, what is the new NPV of the project?
$ ??? million
Place your answer in millions of dollars using at least three decimal places. For example, the answer of nine hundred seventy five thousand would be entered as 0.975 and not as 975000.
Explanation / Answer
The total costs (construction cost) incurred up until point B = 1+2+2 = $ 5 million
If franchise is granted:
Hotel is completed - Hotel Worth = $ 9.2 million and Cost = $ 5million
NPV = (9.2 - 5) = $ 4.2 million
Hotel is not completed - Abandoned Hotel NPV = - $ 1 million
If franchise is not granted:
Hotel is completed - Hotel Worth = $ 3.8 million and Cost = $ 5 million
NPV = (3.8 - 5) = - $ 1.2 million
Hotel is not completed - Abandoned Project NPV = - $ 1 million
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.