0 1 2 3 Project A -$31 $7 $12 $22 Project B -$19 $13 $6 $5 What are the projects
ID: 2675541 • Letter: 0
Question
0 1 2 3
Project A -$31 $7 $12 $22
Project B -$19 $13 $6 $5
What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places.
Project A $ million
Project B $ million
What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places.
Project A $ million
Project B $ million
What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places.
Project A $ million
Project B $ million
What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places.
Project A %
Project B %
What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places.
Project A %
Project B %
What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places.
Project A %
Project B %
Explanation / Answer
a.What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Project A $ million : $0.02 Project B $ million : $3.74 What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Project A $ million : -$0.83 Project B $ million : $1.80 What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places. Project A $ million : -$1.57 Project B $ million : $0.13 b.What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places. Project A % :5.12% Project B % : 15.43% What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places. Project A % :5.12% Project B % : 15.43% What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places. Project A % :5.12% Project B % : 15.43%