0 1 2 3 Project A -$25 $5 $10 $17 Project B -$20 $10 $9 $6 What are the projects
ID: 2713796 • Letter: 0
Question
0 1 2 3
Project A -$25 $5 $10 $17
Project B -$20 $10 $9 $6
What are the projects’ IRRs at each of these WACCs? (Yes, I do need IRRs; not MIRRs. I understand that WACCs don't affect the IRRs, but I don't know the answer. Please show how to determine the answer, and the answer.)
WACC = 5%, NPVs:
Project A = 3.52 million; Project B = 2.86 million
WACC = 10%, NPVs:
Project A = .57 million; Project B = 1.04 million
WACC = 15%, NPVs:
Project A = -1.91 million; Project B = -.54 Million
Explanation / Answer
IRR would be similar in all three case as it does not use WACC, BUT MIRR would be different , So IRR in each situation would be same
Project A
IRR is the rate at which NPV is equal to zero i.e
PV of Cash Outflow = PV of Cash Inflow
25 = 5/(1+r) + 10/(1+r)^2 + 17/(1+r)^3
Using trial run & error method
We get
IRR = 11.10%
Using Excel formula
IRR = irr(values)
IRR = irr({-25,5,10,17})
IRR = 11.10%
Project B
IRR is the rate at which NPV is equal to zero i.e
PV of Cash Outflow = PV of Cash Inflow
20 = 10/(1+r) + 9/(1+r)^2 + 6/(1+r)^3
Using trial run & error method
We get
IRR = 13.18%
Using Excel formula
IRR = irr(values)
IRR = irr({-20,10,9,6})
IRR = 13.18 %
Answer
Projects’ IRRs at each of these WACCs
PROJECT A = 11.10%
PROJECT B = 13.18%
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.