We need someone to supply us with 225,000 cartons of machine screws per year to

ID: 2677323 • Letter: W

Question

We need someone to supply us with 225,000 cartons of machine screws per year to support its manufacturing needs over the next 7 years, and you've decided to bid on the contract. It will cost you $1,230,000 to install the equipment necessary to start production; you'll depreciate this cost straight-line to zero over the project's life. You estimate that in 7 years, this equipment can be salvaged for $75,000. Your fixed production costs will be $360,000 per year, and your variable production costs should be $13.20 per carton. You also need an initial investment in net working capital of $112,500, all of which will be recovered when the project ends. Your tax rate is 32 percent and you require a 13 percent return on your investment. What bid price per carton should you submit (Hint: the NPV)?

Explanation / Answer

bid price per carton should you submit =$31.65

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote