At a required return of 9 percent, what is the NPV of the project? ( Do not roun
ID: 2701428 • Letter: A
Question
At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
At a required return of 28 percent, what is the NPV of the project? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)
At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)
A project that provides annual cash flows of $2,700 for nine years costs $8,800 today.Explanation / Answer
Hi,
Please find the answer as follows:
Part A:
NPV = -8800 + 2700/(1+ .09)^1 + 2700/(1+ .09)^2 + 2700/(1+ .09)^3 + 2700/(1+ .09)^4 + 2700/(1+ .09)^5 + 2700/(1+ .09)^6 + 2700/(1+ .09)^7 + 2700/(1+ .09)^8 + 2700/(1+ .09)^9 = 7387.17
Part B:
NPV = - 8800 + + 2700/(1+ .28)^1 + 2700/(1+ .28)^2 + 2700/(1+ .28)^3 + 2700/(1+ .28)^4 + 2700/(1+ .28)^5 + 2700/(1+ .28)^6 + 2700/(1+ .28)^7 + 2700/(1+ .28)^8 + 2700/(1+ .28)^9 = -202.64
Part C:
Discount Rate = 27.15%
Thanks.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.