Question
Compute the NPV statistics for Project Y and advise whether the firm should accept or reject with the cash flows shown in the chart if the appropriate cost of capital is 12%.
Project Y
Time 0 1 2 3 4
Cash Flow -$11,000 $3,350 $4,180 $1,520 $2,000
In addition to your solution to each computational problem, you must show the supporting work leading to your solution to receive credit for your answer.
Explanation / Answer
AS WE CAN SEE THA NET PRESENT VALUE IS -2324, THE PROJECT SHOULD NOT BE AACEPTED
YEAR CASH FLOW PV FACTOR PV 0 -11000 1 -11000 1 3350 0.893 2991 2 4180 0.797 3332 3 1520 0.712 1082 4 2000 0.636 1271 -2324Related Questions