Tellus Co. manufactures battery operated vehicles that children ride around on.

ID: 2708369 • Letter: T

Question

Tellus Co. manufactures battery operated vehicles that children ride around on. (Similar to Power Wheels)  As a production manager you develop the below value chart:

Operation

Average Number of Days

Receiving materials

3

Storing materials

2

Handling materials

3

Creating the plastic   pieces for the body

6

Assembling the vehicle

2

Electrical work

4

Inspection/Quality   control testing

2

Packaging for   distribution

0.5

Storing product before   distribution

10

a.     What activities listed above are the value-added activities?

b.     How much time is spent in total on value-added activities?

c.     What activities listed above are the non-value-added activities?

d.     How much time is spent in total on non-value-added activities?  

  

Operation

     

Average Number of Days

     

Receiving materials

     

3

     

Storing materials

     

2

     

Handling materials

     

3

     

Creating the plastic   pieces for the body

     

6

     

Assembling the vehicle

     

2

     

Electrical work

     

4

     

Inspection/Quality   control testing

     

2

     

Packaging for   distribution

     

0.5

     

Storing product before   distribution

     

10

   Tellus Co. manufactures battery operated vehicles that children ride around on. (Similar to Power Wheels) As a production manager you develop the below value chart: What activities listed above are the value-added activities? How much time is spent in total on value-added activities? What activities listed above are the non-value-added activities? How much time is spent in total on non-value-added activities?

Explanation / Answer

value added activities are

Creating the plastic pieces for the body + Assembling the vehicle + Electrical work + Inspection/Quality control testing + Packaging for distribution

time spent = 6+2+4+2+0.5 = 14.5 days


rest activities are non value added.

and time spent on them are sum of their individual times

= 3+2+3+10 = 18