Calculate the MIRR of the project using the discounting approach. (Do not round
ID: 2709563 • Letter: C
Question
Calculate the MIRR of the project using the discounting approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
Calculate the MIRR of the project using the reinvestment approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
Calculate the MIRR of the project using the combination approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
RAK Corp. is evaluating a project with the following cash flows:
Explanation / Answer
1. IRR = 31.92%
2. MIRR using reinvestment approach = 22.46%
3. MIRR using combination approach = 19%