Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Wheel has two other possible investment opportunities, which are mutually exclus

ID: 2717840 • Letter: W

Question

Wheel has two other possible investment opportunities, which are mutually exclusive, and independent of Investment A above. Both investments will cost $120,000 and have a life of 6 years. The after tax cash flows are expected to be the same over the six year life for both projects, and the probabilities for each year's after tax cash flow is given in the table below.

Investment B

Investment C

Probability

After Tax
Cash Flow

Probability

After Tax
Cash Flow

0.25

$20,000

0.30

$22,000

0.50

32,000

0.50

40,000

0.25

40,000

0.20

50,000

What is the expected value of each project’s annual after tax cash flow? Justify your answers and identify any conflicts between the IRR and the NPV and explain why these conflicts may occur.

Assuming that the appropriate discount rate for projects of this risk level is 8%, what is the risk-adjusted NPV for each project? Which project, if either, should be selected? Justify your conclusions.

Investment B

Investment C

Probability

After Tax
Cash Flow

Probability

After Tax
Cash Flow

0.25

$20,000

0.30

$22,000

0.50

32,000

0.50

40,000

0.25

40,000

0.20

50,000

Explanation / Answer

NPV is the difference between the present value of cash inflows and cash outflows. It can be calculated with the use of following formula:

NPV = Cash Flow Year 0 + Cash Flow Year 1/(1+Discount Rate)^1 + Cash Flow Year 2/(1+Discount Rate)^2 + Cash Flow Year 3/(1+Discount Rate)^3

__________

Step 1: Calculate Cash Flow for Each Year

Cash Flow Year 0 = Initial Investment = -$1,500,000

Annual After-Tax Flow (Year 1 to Year 3) = (Incremental Revenues - Incremental Costs - Depreciation)*(1-Tax Rate) + Depreciation

where Depreciation = Initial Investment/Life of the Project

Using the information provided, we get,

Annual After-Tax Flow (Year 1 to Year 3) = (1,200,000 - 600,000 - 1,500,000/3)*(1-35%) + 1,500,000/3 = $565,000

__________

Step 2: Calculate NPV

Using the values calcuated in Step 1 in the formula for NPV, we get,

NPV = -1,500,000 + 565,000/(1+6%)^1 + 565,000/(1+6%)^2 + 565,000/(1+6%)^3 = $10,251.75

Since, the NPV is positive, it is economically viable to accept the project.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote