What is Project B\'s discounted payback? Round your answer to four decimal place
ID: 2719853 • Letter: W
Question
What is Project B's discounted payback? Round your answer to four decimal places. Do not round your intermediate calculations.
Explanation / Answer
Project A
Project B
Year 0 Year 1 Year 2 Year 3 Year 4 Dec-15 Dec-16 Dec-17 Dec-18 Dec-19 Cash flow -1200 700 355 250 300 Discount rate % 11.0% present value of cashflows -1200 630.6 288.1 182.8 197.6 NPV 99.17 IRR 15.63% Cumulative Cash Flow -1200.00 -500.00 -145.00 105.00 405.00 Discounted cumulative cash flows -1200.00 -569.37 -281.24 -98.45 99.17 Profitability Index = PV of future cashflows/initial investment 1.08 Paybac period Discounted payback period 3.5Related Questions