AC Slater and Zach Morris are partners in a firm. They are trying to decide on a
ID: 2723775 • Letter: A
Question
AC Slater and Zach Morris are partners in a firm. They are trying to decide on a new project to take on, but they can only afford one project. They both have favorites as listed in the table below. Assuming a 10% discount rate, which project should they choose? Investment Year 1 Year 2 Year 3 Year 4 AC’s -400 200 200 200 Zach’s -500 175 175 175 175
Question 2 options:
A.) Zach’s because it has the highest NPV
B.)AC’s because it has the highest NPV
C.)Zach’s because the initial investment is lower
D.)Neither, both NPV’s are too low.
Explanation / Answer
AC NPV=-400+200/1.10^1+200/1.10^2+200/1.10^3=97.37
zach =-500+175/1.10^1+175/1.10^2+175/1.10^3+175/1.10^4=54.73
answer
B.)AC’s because it has the highest NPV