Question
The following are the cash flows of two projects: Year Project A Project B 0 $220 $220 1 100 120 2 100 120 3 100 120 4 100 a. Calculate the NPV for both projects if the discount rate is 10%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV A $ B b. Suppose that you can choose only one of these projects. Which would you choose? Project A Project B NeitherThe following are the cash flows of two projects:
Explanation / Answer
a.
Project NPV
Project A $96.99
Project B $78.42
b. Since Project A has higher NPV it should be accepted.
Year Project A Project B PV Factor @ 10% PV of Project A PV of Project B 0 -220 -220 1 -220 -220 1 100 120 0.9091 90.91 109.09 2 100 120 0.8264 82.64 99.17 3 100 120 0.7513 75.13 90.16 4 100 0.6830 68.30 0.00 Net Present Value 96.99 78.42Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.