The following are the cash flows of two projects: Year Project A Project B 0 $26
ID: 2772230 • Letter: T
Question
The following are the cash flows of two projects: Year Project A Project B 0 $260 $260 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the discount rate is 11%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV A $ B b. Suppose that you can choose only one of these projects. Which would you choose? Project A Project B Neither The following are the cash flows of two projects:Explanation / Answer
a.Computation of Net present value
Year Project A discount@11% Present value of Project B discount@11% Present value of
cash inflows cash inflows
1 140 0.9009 126.13 160 0.9009 144.14
2 140 0.8116 113.62 160 0.8116 129.86
3 140 0.7312 102.37 160 0.7312 116.99
4 140 0.6587 92.22 - - -
Present value of cash inflows 434.34 390.99
less: initial investment (260) (260)
Net present value 174.34 130.99
b. Project A has highest NPV is 174.34.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.