An all-equity firm is considering the following projects: The T-bill rate is 5 p
ID: 2725027 • Letter: A
Question
An all-equity firm is considering the following projects:
The T-bill rate is 5 percent, and the expected return on the market is 12 percent.
Compared with the firm's 12 percent cost of capital, Project W has a (higher/lower) expected return, Project X has a (higher/lower) expected return, Project Y has a (higher/lower) expected return, and Project Z has a (higher/lower) expected return.
Project W should be (accepted/rejected) , Project X should be (accepted/rejected), Project Y should be (accepted/rejected), and Project Z should be (accepted/rejected).
If the firm's overall cost of capital were used as a hurdle rate, Project W would be (correctly accepted/correclty rejected/incorrectly accepted/incorrecltyrejected), Project X would be (correctly accepted/correclty rejected/incorrectly accepted/incorrecltyrejected), Project Y would be (correctly accepted/correclty rejected/incorrectly accepted/incorrecltyrejected), and Project Z would be (correctly accepted/correclty rejected/incorrectly accepted/incorrecltyrejected).
An all-equity firm is considering the following projects:
Explanation / Answer
Ke = Rf + Betal(Rm -Rf)
for project W : Ke = 5% + 0.61(12%-5%) = 9.27%
for project X : Ke = 5% + 0.0.85(12%-5%) = 10.95%
for project Y : Ke = 5% + 1.17(12%-5%) = 13.19%
for project Z : Ke = 5% + 1.55(12%-5%) = 15.85%
a) Project W: Lower Expected return
Project X: Lower Expected return
Project Y: Higher Expected return
Project Z: Higher Expected return
b) Project W: Rejected
Project X: Rejected
Project Y: Accepted
Project Z: Accepted
c) Project W: Correctly Rejected
Project X: Correctly Rejected
Project Y:Correctly Accepted
Project Z: Correctly Accepted
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.