Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: This exercise contains only parts b, c, and d. The critical activities for the leadership training program development project are B - D - E - G. The project length for the leadership training program development project = days.

Explanation / Answer

The project length = Length of critical activities

= B+D+E+G

= 5+10+4+10

= 29 days