Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: This exercise contains only parts b, c, and d. The critical activities for the leadership training program development project are B - D - E - G. The project length for the leadership training program development project = days.Explanation / Answer
The project length = Length of critical activities
= B+D+E+G
= 5+10+4+10
= 29 days
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.