Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
A) The critical activities for the leadership training program development project are?
B) The project length for the leadership training program development project?
D) Slack time for each of the activities is(EACH INDIVIDUAL SLACK TIME)?
Activity Immediate Predecessor(s) Time(days) A - 3 B - 6 C - 2 D B 10 E A, D 3 F C 6 G E, F 8Explanation / Answer
The precedence diagram of activities as follows :
A-E-G = 3 + 3 + 8 = 14days
B-D-E-G = 6 + 10 + 3 + 8 = 27 days
C-F-G = 2 + 6 + 8 = 16 days
Out of above , activities B-D-E-G has the longest duration of 27 days and hence forms the critical path for the project
Slack time of activity A
= Duration B-D-E-G - Duration A-E-G
= 27 – 14
= 13 days
Slack time of C, F
= Duration B-D-E-G – Duration C-F-G
= 27 – 16
= 11 days