Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Down Under Boomerang, Inc., is considering a new three-year expansion project th

ID: 2743620 • Letter: D

Question

Down Under Boomerang, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $2.79 million. The fixed asset will be depreciated straight-line to zero over its three-year tax life, after which it will be worthless. The project is estimated to generate $2,110,000 in annual sales, with costs of $805,000. The tax rate is 35 percent and the required return is 12 percent.

What is the project’s NPV? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Explanation / Answer

Answer:

Using Tax shield approach to calculating OCF:

OCF= (sales- Costs)(1-tax) + tax*Depreciation

OCF= ($2,110,000- $805,000) (1-0.35) +0.35($2,790,000/3)

OCF= $848,250 +$325,500

OCF =$1,173,750

So NPV of the Project is:

NPV= - $2,790,000 + $1,173,750*PVIFA(12%, 3)

NPV = - $2,790,000 + $1,173,750 * 2.4018

NPV = - $2,790,000 + $2,819,112.75

NPV = $29,112.75

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote