Consider the project. Activity 1 2 3 4 5 6 7 8 9 10 Predecessors 6 8 4,8 --- 1,2
ID: 2747905 • Letter: C
Question
Consider the project.
Activity
1
2
3
4
5
6
7
8
9
10
Predecessors
6
8
4,8
---
1,2
8
5,9
---
1,6
4
Duration
5
1
6
1
5
4
5
2
5
2
Early Start
Early Finish
Multiple Choice Questions.
Circle One
A B C D
1. What is the time of completion?
(A) 22 (B) 23 (C) 21 (D) none of the above
A B C D
2. What is the early start of activity 2?
(A) 4 (B) 2 (C) 3 (D) none of the above
Activity
1
2
3
4
5
6
7
8
9
10
Predecessors
6
8
4,8
---
1,2
8
5,9
---
1,6
4
Duration
5
1
6
1
5
4
5
2
5
2
Early Start
Early Finish
Explanation / Answer
Q1 - There are two critical paths of the project - 8-6-1-5-7 and 8-6-1-9-7. Time of completion is 21
Q2 - Earliest start of Activity 2 is at the completion of Activity 8, i.e. 2
Related Questions