Please see the correct answers given in the box under the question. Just need to

ID: 2748354 • Letter: P

Question

Please see the correct answers given in the box under the question. Just need to know why those are the right answers. Please be as descriptive as possible-thanks!

Question 1 Partially correct 0.67 points out of The gross requirements for items A and B are specified for weeks 1 through 12 in the tables that follow. The product structure for each of the two items is given in two figures in which the lead time for each item and constituent part is specified within brackets. Product Structure for items A and H 2.00 T11 Flag quesion ILT 2 Item A, Level 0 01 02 03 04 05 06 07 08 09 10 11 12 0 0000 O 0 0 50 75 50 25 ross req uirements. Planned order release Item H, Level 0 01 02 03 04 05 06 07 08 09 10 11 12 0 00 0 0 0 25 50 50 25 ross requirements. Planned order release Item C, Level 1 01 02 03 04 05 06 07 08 09 10 11 12 ross requir Planned order release Determine the planned order releases for item C, and then select the correct number of units for the planned order release in specified uirements. weeks: The planned order release for item C in week 5 is The planned order release for item C in week 6 is The planned order release for item C in week 7 is50 The planned order release for item C in week 8 is The planned order release for item C in week 9 is The planned order release for item C in week 10 is 100 75 125 The correct answer is: The planned order release for item C in week 5 is 0, The planned order release for item C in week 6 is 75, The planned order release for item C in week 7 is 125, The planned order release for item C in week 8 is 100, The planned order release for item C in week 9 is 50, The planned order release for item C in week 10 is -0

Explanation / Answer

Projected On Hand Calculation = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement (If the above calculation results in negative amount, then such amount is taken as Net Requirement, else 0) Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed, Here 1 week before Item = A, Level = 0 LT : 1 Week Period 0 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 0 0 0 0 0 50 75 50 25 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 0 0 Net Requirements 0 0 0 0 0 0 0 0 50 75 50 25 Planned Receipts 0 0 0 0 0 0 0 0 50 75 50 25 Planned Order Release 0 0 0 0 0 0 0 50 75 50 25 0 Item = H, Level = 0 LT : 1 Week Period 0 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 0 0 0 0 0 25 50 50 25 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 0 0 Net Requirements 0 0 0 0 0 0 0 0 25 50 50 25 Planned Receipts 0 0 0 0 0 0 0 0 25 50 50 25 Planned Order Release 0 0 0 0 0 0 0 25 50 50 25 0 Item C is required for A and H. 1 unit is required for both 1 Unit of A and H C is required when Order Release of A and H Happens Week 8 = 50 + 25 = 75 Week 9 = 75 + 50 =125 Week 10 = 50 + 50 = 100 Week 11 = 25 + 25 = 50 Lead time is two weeks, so order needs to be placed two prior of order receipt Item = C, Level = 1 LT : 2 Weeks Period 0 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 0 0 0 0 75 125 100 50 0 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 0 0 Net Requirements 0 0 0 0 0 0 0 75 125 100 50 0 Planned Receipts 0 0 0 0 0 0 0 75 125 100 50 0 Planned Order Release 0 0 0 0 0 75 125 100 50 0 0 0