A project under consideration has an internal rate of return of 14% and a beta of 0.6. The risk-free rate is 9%, and the expected rate of return on the market portfolio is 14%. a-1. Calculate the required return. Required return % a-2. Should the project be accepted? Yes No b-1. Calculate the required return if its beta is 1.6. Required return % b-2. Should the project be accepted? Yes No A project under consideration has an internal rate of return of 14% and a beta of 0.6. The risk-free rate is 9%, and the expected rate of return on the market portfolio is 14%.Explanation / Answer
a-1) Required return = Risk-free rate + Beta * (Expected rate of return on market - Risk-free rate)
= 9 + 0.6 ( 14 - 9)
= 12%
a-2) Project should be accepted as the actual return of 14 % (Internal rate of return) is greater than the required return of 12%.
b-1) If New Beta is 1.6
Required return = Risk-free rate + Beta * (Expected rate of return on market - Risk-free rate)
= 9 + 1.6 ( 14 - 9)
= 17 %
b-2) Project should not be accepted as the actual return of 14 % (Internal rate of return) is less than the required return of 17 %.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.