Question 7. (15 points) Marcel Corporation is considering a silver mining projec
ID: 2790959 • Letter: Q
Question
Question 7. (15 points) Marcel Corporation is considering a silver mining project would cost $50 million today and generate positive cash flows of $15 million a year at the end of each of the next 5 years. The project's cost of capital is 10%.
a. Calculate the project's NPV if the company proceeds now.
b. The company is fairly confident about its cash flow forecast, but expects to have better price information in 2 years. The company believes the cost will be $55 million in 2 years. It estimates there is a 90% change CFs will be $16 million for 5 years and a 10% change CFs will be $12 million for 5 years. Should the company proceed with the project now or wait 2 years until it has better information?
Explanation / Answer
NPV=-50+15/1.1+15/1.1^2+15/1.1^3+15/1.1^4+15/1.1^5=6.8618 million
Expected cash flows for 5 years=0.9*16+0.1*12=15.6 million
Expected NPV in 2 years=-55+15.6/1.1+15.6/1.1^2+15.6/1.1^3+15.6/1.1^4+15.6/1.1^5=4.136274
As the expected NPV in 2 years is less than present NPV and then present value of expected NPV in 2 years will be even more less than present NPV..Hence, we should not wait but we should do the project now.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.