Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

a) Suppose the firm uses the IRR decision rule. Should the firm accept the proje

ID: 2797204 • Letter: A

Question

a) Suppose the firm uses the IRR decision rule. Should the firm accept the project if the required return is 8%?

b.)Suppose the firm uses the IRR decision rule. Should the firm accept the project if the required return is 11%?

c.) Suppose the firm uses the NPV decision rule. Should the firm accept the project if the required return is 9%?

d.) Suppose the firm uses the NPV decision rule. Should the firm accept the project if the required return is 22%?

e.) Suppose the firm uses the NPV decision rule. Should the firm accept the project if the required return is 0%?

f.) Suppose the firm uses the PI decision rule. Should the firm accept the project if the required return is 7%?

g.) Suppose the firm uses the PI decision rule. Should the firm accept the project if the required return is 16%?

Year Cash Flow 0 -30,000 1 20,000 2 5,000 3 10,000

Explanation / Answer

IRR is the rate at which NPV = 0

NPV is calculated by discounting the cashflows

PV = C/(1+r)^n

C - Cashflow

r - Discount rate

n - years to the cashflow

a.

NPV = -30000 + 20000/(1+IRR)^1 + 5000/(1+IRR)^2 + 10000/(1+IRR)^3 = 0

By trail and error, IRR = 9.61%

Accept the project since IRR is greater than required rate.

B.

Reject the project since IRR is less than required rate of 11%.

C.

Accept the project as NPV is positive.

D.

Reject the project since NPV is negative

E.

Accept the project since NPV is positive.

F.

PI = (NPV+Initial investment)/Initial investment

PI = (1221.76+30000)/30000 = 1.04

Accept the project since PI is greater than 1.

g.

PI = (-2636.23+30000)/30000 = 0.91

Reject the project since PI is less than 1.

Rate 9.00% Year Cashflow (A) Discount rate = 1/(1+r)^(n) Present value of cashflow = A*discount rate 0 -30000.00 1.00 -30000.00 1 20000.00 0.92 18348.62 2 5000.00 0.84 4208.40 3 10000.00 0.77 7721.83 4 0.00 0.71 0.00 NPV 278.86