Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

If projects are mutually exclusive, only one project can be chosen. The internal

ID: 2798150 • Letter: I

Question

If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) $200 Year Project Y Project z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project Z . If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and IRR methods agree or conflict? O The methods conflict. O The methods agree. -2001 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent)

Explanation / Answer

If the cross rate on the NPV profile is below the horizontal axis, the method will sometime agree.
Because, We need to choose only one project from the two mutually exclusive projects. The IRR and NPV methods always will not choose the same project due to timing and size of the project.


The correct option is the methods agree.

Explanation:
The main conflict between NPV and IRR methods are timing and size differences between mutually exclusive projectss.
Here, we can see that the project Y’s cash ows occur late in the project's life ($1,500 / $2,200 = 68.18% occurring in the last two years), whereas the bulk of project Z’s cash ows occur relatively early in the project’s life ($1,500/ $2,000 = 75.0% occurring in the rst two years).

Thus, Project Y has greater undiscounted cash ows, but most of its cash ows occur further into the future.
Based on the required rate of return ,If return increases then project Y’s NPV decreases at a far greater rate than project Z’s NPV.

Cash flows

PV of cash flows

Year

Project Y

Project Z

Discounting factor at 14%

Project Y

Project Z

0

-1500

-1500

1

-1500

-1500

1

200

900

0.877192982

175.438596

789.4736842

2

400

600

0.769467528

307.787011

461.6805171

3

600

300

0.674971516

404.98291

202.4914549

4

1000

200

0.592080277

592.080277

118.4160555

-19.711205

72.06171163


At a required rate of retum of 14%, project Z has a higher NPV because its NPV prole is higher than project Y's NPV prole. Therefore, NPV method would choose project Z over project Y.
When comes to IRR for project Y it is 13% and for project Z it is 17%.
Therefore, the NPV and IRR methods agree with each other.

A key to resolving this conict is the assumed reinvestment rate. The NPV calculation implicitly assumes that intermediate cash ows are reinvested at the required rate of return , and the IRR calculation assumes that the rate at which cash ows can be reinvested is the internal rate of return (IRR).
As a result, when evaluating mutually exclusive projects, the NPV method is usually the better decision criterion.

Cash flows

PV of cash flows

Year

Project Y

Project Z

Discounting factor at 14%

Project Y

Project Z

0

-1500

-1500

1

-1500

-1500

1

200

900

0.877192982

175.438596

789.4736842

2

400

600

0.769467528

307.787011

461.6805171

3

600

300

0.674971516

404.98291

202.4914549

4

1000

200

0.592080277

592.080277

118.4160555

-19.711205

72.06171163

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote