* CS Macromedia Cornet * a correct *- C Home | Chegg.com x 2 Home | myluvu x 0 McGraw-Hill Connect x Connect * - e a Secure | https://newconnect.mheducation.com/flow/connect.html # Apps o YouTube E ESPN O CHASE & BB M Gmail ICH IMDb D NGEQUITIES NBA.com a Amazon a Forex Factory Uvu vsu ws Y Fantasy W 801 Skiing Im - X & * : » D Other bookmarks HW 14 0 Saved Help Save & Exit Submit Check my work Problem 14.7 25 points Compute the takt time for a system where the total time per shift is 400 minutes, there is one shift, and workers are given 3 14-minute breaks and 40 minutes for lunch. Daily demand is 356 units. (Round your answer to 2 decimal places.) Takt time Jminutes per cycle ok Print References Reference links 14.3 Building blocks O Type here to search e 12:54 PM = a D E 9 I 12/6/2017Explanation / Answer
Net time per day = (Total time - rest breaks - lunch)*number of shifts
= (400 - 3*14 - 40)*1 = 318 minutes per day
Take time = 318 min/356 units = 0.8933 minutes per cycle.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.