Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider a project to supply Detroit with 40,000 tons of machine screws annually

ID: 2799002 • Letter: C

Question

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $300 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value of $600,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $370 per ton. The engineering department estimates you will need an initial net working capital investment of $500,000. You require a return of 15 percent and face a marginal tax rate of 30 percent on this project. a. Suppose you’re confident about your own projections, but you’re a little unsure about Detroit’s actual machine screw requirement. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places, e.g., 32.16.) OCF/Q $ b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places, e.g., 32.16.) NPV/Q $ c. Given the sensitivity number you calculated, what is the minimum level of output below which you wouldn’t want to operate? (Do not round intermediate calculations and round your final answer to the nearest whole number, e.g., 32) Minimum level of output

Explanation / Answer

Calculation Of Operating Cash flows

40000 Unit

30000 Unit

Particulars

Amount

Amount

Revenue 40,000Tonne * 370

$ 148,00,000.00

$ 111,00,000.00

Variable Cost per Tonne 40000*300

$ 120,00,000.00

$    90,00,000.00

Contribution

$    28,00,000.00

$    21,00,000.00

(-) Annual fixed cost

$      7,00,000.00

$      7,00,000.00

(-)Depreciation

$      7,66,666.67

$      7,66,666.67

PBT

$    13,33,333.33

$      6,33,333.33

(-) Tax 30%

$      4,00,000.00

$      1,90,000.00

PAT

$      9,33,333.33

$      4,43,333.33

OCF = PAT+ Depreciation

$    17,00,000.00

$    12,10,000.00

a) For calculating change in operating cash flows units taken be 30000 and cash flows calculated as above

Sensitivity of the project OCF to changes in quantity = (1,700,000-1,210,000)/ (40000-30000)

= $ 49 for 1 quantity changed.

b) Calculation of NPV

Cash outflow = Cost of machine + working capital requirement = $ 5,700,000

Cash inflow Terminal = Salvage Value+ Working capital surrendered = $600,000(1-0.3) +$500,000 = $920,000

At 40000 units NPV = 1,700,000*PVAF (15%, 6) + 920,000*PVIF (15%, 6) -$ 5,700,000

PVAF (15%, 6) = 3.784 from PVAF table, PVIF (15%, 6) = 0.432 referring PVIF table

NPV= 1,700,000*3.784 + 920,000*0.432 - 5,700,000

NPV= 1,130,240

At 30000 units NPV= 1,210,000*PVAF (15%, 6) + 920,000*PVIF (15%, 6) -$ 5,700,000

= - 723,920

Sensitivity of NPV to change in units= [1130240-(-723920)]/ [40000-30000]

= $ 185.416

c) So for every quantity change NPV changes by $ 185.416, for minimum quantity we can divide total NPV of 40000 units with npv sensitivity to find out how many units can be reduced

Q=1130240/185.416= 6095.7 units

I.e. Minimum units to operate where NPV is 0 is 40000units- 6095.7 units

=33,904.3 units

Calculation Of Operating Cash flows

40000 Unit

30000 Unit

Particulars

Amount

Amount

Revenue 40,000Tonne * 370

$ 148,00,000.00

$ 111,00,000.00

Variable Cost per Tonne 40000*300

$ 120,00,000.00

$    90,00,000.00

Contribution

$    28,00,000.00

$    21,00,000.00

(-) Annual fixed cost

$      7,00,000.00

$      7,00,000.00

(-)Depreciation

$      7,66,666.67

$      7,66,666.67

PBT

$    13,33,333.33

$      6,33,333.33

(-) Tax 30%

$      4,00,000.00

$      1,90,000.00

PAT

$      9,33,333.33

$      4,43,333.33

OCF = PAT+ Depreciation

$    17,00,000.00

$    12,10,000.00

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote