Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

You are considering two mutually exclusive projects with the following cash flow

ID: 2814765 • Letter: Y

Question

You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent?

Year Cash flow (A) Cash flow (B)

0   -$80,000   -$80,000

1              31,000        0

2     31,000                                      0

3                31,000                           110,000

accept project A as it always has the higher NPV

accept project B as it always has the higher NPV

accept B at 8.5 percent and A at 13 percent

accept B at 8.5 percent and neither at 13 percent

a.

accept project A as it always has the higher NPV

b.

accept project B as it always has the higher NPV

c.

accept B at 8.5 percent and A at 13 percent

d.

accept B at 8.5 percent and neither at 13 percent

Explanation / Answer

d. accept B at 8.5 percent and neither at 13 percent Statement showing Cash flows Project A Project B Particulars Time PVf 8.5% Amount PV Cash Outflows                             -                 1.00            (80,000.00)                  (80,000.00)            (80,000.00)            (80,000.00) PV of Cash outflows = PVCO                  (80,000.00)            (80,000.00) Cash inflows                         1.00          0.9217              31,000.00                    28,571.43                              -                                -   Cash inflows                         2.00          0.8495              31,000.00                    26,333.11                              -                                -   Cash inflows                         3.00          0.7829              31,000.00                    24,270.15            110,000.00              86,119.89 PV of Cash Inflows =PVCI                    79,174.69              86,119.89 NPV= PVCI - PVCO                        (825.31)                 6,119.89 Statement showing Cash flows Project A Project B Particulars Time PVf 13% Amount PV Cash Outflows                             -                 1.00            (80,000.00)                  (80,000.00)            (80,000.00)            (80,000.00) PV of Cash outflows = PVCO                  (80,000.00)            (80,000.00) Cash inflows                         1.00          0.8850              31,000.00                    27,433.63                              -                                -   Cash inflows                         2.00          0.7831              31,000.00                    24,277.55                              -                                -   Cash inflows                         3.00          0.6931              31,000.00                    21,484.56            110,000.00              76,235.52 PV of Cash Inflows =PVCI                    73,195.73              76,235.52 NPV= PVCI - PVCO                    (6,804.27)              (3,764.48)

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote