You are estimating the install hours for an electronics upgrade based on the num
ID: 2958037 • Letter: Y
Question
You are estimating the install hours for an electronics upgrade based on the number of components affected. The upgrade for which you are estimating affects 12 components. Given the following equation, select the correct response from each pair.Install Hours = 2.65 + 2.15 (# Components)
The independent variable is # Components
The independent variable is Install Hours
The slope is 2.15
The slope is 2.65
The estimated install hours for your upgrade is 57.6 hours
The estimated install hours for your upgrade is 28.45 hours
Explanation / Answer
The independent variable is # Components
The slope is 2.15
The estimated install hours for your upgrade is 28.45 hours
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.