Question
Computer upgrades have a nominal listed I time of 80 minutes. Samples of five o tions each have been taken, and the results are as 79.280.5 79.6 78.9 80.5 79.7 78.8 78.7 79.6 79.4 79.6 80.6 80.0 81. 80.4 79.7 80.4 80.5 78.480.4 80.3 79.4 80.8 8.0 81.080.1 80.8 80.6 78.8 81.1 Factors for three-sigma control limits for and R charts FACTORS FOR R CHARTS Number of observations chart, in Subgroup42 Factor for Control Limit, Control 1.88 1.02 0.73 0.58 0.48 3.27 2.57 2.28 2.11 2.00 1.92 1.86 1.82 1.78 8.08 0.37 0.34 0.31 0.29 0.18 0.22 0.26 10Explanation / Answer
R
R= 9.5/5= 1.9
UCL= D4*R= 2*1.9=3.8
LCL= D3*R= 0*1.9=0
X-bar
X= 399.8/5= 79.96
UCL= X+A2*R= 79.96+0.48*1.9= 80.872
LCL= X-A2*R= 79.96-0.48*1.9= 79.048
D3, D4 and A2 are for n=6 because we have six sub groups in each sample.
1 2 3 4 5 6 X R 79.2 80.5 79.6 78.9 80.5 79.7 79.73333333 1.6 78.8 78.7 79.6 79.4 79.6 80.6 79.45 1.9 80 81 80.4 79.7 80.4 80.5 80.33333333 1.3 78.4 80.4 80.3 79.4 80.8 80 79.88333333 2.4 81 80.1 80.8 80.6 78.8 81.1 80.4 2.3 X R 79.96 1.9Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.