Below you have a payoff table for a project that is under consideration. Possibl
ID: 3071849 • Letter: B
Question
Below you have a payoff table for a project that is under consideration.
Possible future demand
Alternatives low med high
Project A 50 60 85
Project B 60 60 60
Project C 40 50 90
Probabilities 0.2 0.5 0.3
1. Which alternative would you select given the probabilities in the table above and the Expected Value Approach? (Project A,B, or C?)
Explanation / Answer
Expected value for project A = 50(0.2) + 60(0.5) + 85(0.3) = 65.5
Expected value for project B = 60(0.2) + 60(0.5) + 60(0.3) = 60
Expected value for project C = 40(0.2) + 50(0.5) + 90(0.3) = 60
Since the expected value in case of project A is highest, project A must be chosen.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.