Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 18 A large hospital uses a certain intravenous solution that it maintai

ID: 3074721 • Letter: Q

Question

Question 18

A large hospital uses a certain intravenous solution that it maintains in inventory. Assume the hospital uses reorder point method to control the inventory of this item. Pertinent data about this item are as follows:

------------------------------------------------------------

Forecast of demanda = 1,000 units per week

Forecast errora, std. dev. =100 units per week

Lead time = 4 weeks

Carrying cost = 25 % per year

Purchase price, delivered = $52 per unit

Replenishment order cost = $20 per order

Stockout cost = $10 per unit

In-stock Probability during the lead time =90%

a Normally distributed

------------------------------------------------------------

Due to possible rounding effect, please pick the closest number in the following options.

Question 19

If the hospital orders 400 units each time, what’s the total annual costs (holding cost + ordering cost + stock-out cost) excluding purchasing costs?

Question 19 options:

10000

21008

31008

42016

Use the following information to answer questions 17-20.

A large hospital uses a certain intravenous solution that it maintains in inventory. Assume the hospital uses reorder point method to control the inventory of this item. Pertinent data about this item are as follows:

------------------------------------------------------------

Forecast of demanda = 1,000 units per week

Forecast errora, std. dev. =100 units per week

Lead time = 4 weeks

Carrying cost = 25 % per year

Purchase price, delivered = $52 per unit

Replenishment order cost = $20 per order

Stockout cost = $10 per unit

In-stock Probability during the lead time =90%

a Normally distributed

------------------------------------------------------------

Due to possible rounding effect, please pick the closest number in the following options.

Question 20

If the lead time is normally distributed with a mean of 4 weeks and a standard deviation of 0.5 weeks, what’s the reorder point?

Question 20 options:

4689

4129

5188

6000

10000

21008

31008

42016

Explanation / Answer

17.

Weekly demand forecast, d = 1000
StDev of the weekly forecast, = 100
Average lead time, L = 4 weeks
Service level = 0.90 so Z = NORMSINV(0.90) = 1.28

ROP = d * L + Z * * L = 1000*4 + 1.28*100*SQRT(4) = 4,256

18.

Normal loss function, L(Z) corresponding to 90% serivce level = 0.048

Expected shortage per cycle (ESC) = L(Z) * * L = 0.0473*100*SQRT(4) = 9.6

Annual shotage = ESC x no. of cycles annually = 9.6 x (52000/400) = 1248

19.

Shortage cost = Annual shortage x shortage cost per unit = 1248 x $10 = $12,480

Order quantity, Q = 400
Holding cost per unit per annum, H = $52 * 25% = $13
Annual demand, D = 1000 x 52 = 52,000
Ordering cost, S = $20

Cycle stock holding cost = Q * H/ 2 = 400*13/2 = $2,600

Ordering cost = (D/Q) * S = (52000 / 400) * 20 = $2,600

Safety stock cost = Safey stock * H = 1.28*100*SQRT(4) * 13 = $3,328

Total cost = $2,600 + $2,600 + $12,480 + $3,328 = $21,008

20.

L = 4
L = 0.5

The following formula for ROP will apply.

ROP = d * L + Z * (2.L + d2.L2)= 1000*4 + 1.28*SQRT((100^2)*4 + (1000*0.5)^2) =4,689

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote