Activity Start A B C D E F G H End Time 0 3.68 1.37 3.69 6.15 4.65 6.87 4.68 2.6

ID: 3177097 • Letter: A

Question

Activity

Start

A

          B

         C

        D              

E

F

          G

          H

End

Time             

0           

3.68

        1.37

        3.69

       6.15

4.65         

6.87

        4.68

         2.65      

0


a) The Project Completion time = __________(in 2 decimal places)

b) The Earliest Start time, ES, of Activity G = ________ (in 2 decimal places)

c) The Latest Finish time, LF, of Acitivity C = _________ (in 2 decimal places)

d) The critical activities are = __________ (ex. type in critical activities as ABCD, no comma, no space)

Activity

Start

A

          B

         C

        D              

E

F

          G

          H

End

Time             

0           

3.68

        1.37

        3.69

       6.15

4.65         

6.87

        4.68

         2.65      

0

webapps assessment p c VITECEZ TV player Take Test S4AT x What is the Relation Question Completion Status: Start End Activity Start 3.68 3.69 4.65 6.87 a) The Project Completion time

Explanation / Answer

a)  The Project Completion time = 19.35

b) The Earliest Start time, ES, of Activity G = 12.02

c) The Latest Finish time, LF, of Acitivity C = 9.83

d) The critical activities are = ACEGH

Activity time ES EF LS LF A 3.68 0 3.68 2.46 6.14 B 1.37 0 1.37 4.5 5.87 C 3.69 3.68 7.37 6.14 9.83 D 6.15 1.37 7.52 5.87 12.02 E 4.65 7.37 12.02 7.37 12.02 F 6.87 7.37 14.24 9.83 16.7 G 4.68 12.02 16.7 12.02 16.7 H 2.65 16.7 19.35 16.7 19.35