Could you answer this question in excel with full explanation please. Thank you
ID: 327261 • Letter: C
Question
Could you answer this question in excel with full explanation please. Thank you
Schedule the following 6 jobs through two machines in sequence to minimize the total processing time using Johnson's Rule.
(all times in hours)
Job
Machine 1
Machine 2
A
5
2
B
16
15
C
1
9
D
12
11
E
17
3
F
18
7
Determine the amount if idle time for Machine 2 and before which jobs does this idle time occur?
Schedule the following 6 jobs through two machines in sequence to minimize the total processing time using Johnson's Rule.
(all times in hours)
Job
Machine 1
Machine 2
A
5
2
B
16
15
C
1
9
D
12
11
E
17
3
F
18
7
Determine the amount if idle time for Machine 2 and before which jobs does this idle time occur?
Explanation / Answer
We find out the sequence by checking going to the least numbers first and putting them in front if they are on Machine 1 and at back if they are on machine 2.
We get the following job- machine number combinations by following this logic:
C- 1,A- 2,E-2,F-2,D-2 and then we are left with B
Therefore the sequence comes out to be:
CBDFEA
Let us run this sequence through the machine:
Therefore Machine 2 is Idle as Job C ,B,F,E,A are being processed at Machine 1.
Total Idle time= 1+7+4+10+2= 24 Hours
Job Processing at Machine 1 C B D F E A Machine1 1 16 12 18 17 5 Machine2 9 15 11 7 3 2 Idle time for Machine 2 1 7 0 4 10 2 0Related Questions