1.You are a subcontractor who performed work on a privately-owned commercial con

ID: 327883 • Letter: 1

Question

1.You are a subcontractor who performed work on a privately-owned commercial construction project in Ohio. The owner properly filed a Notice of Commencement, and you filed your Notice of Furnishing the day you started work on the project. Your last day of work on the project was 80 days ago. You’ve invoiced for your last month’s payment, but the GC still hasn’t paid—they keep giving you excuses and saying that “the check will be in the mail soon.” Can you put some pressure on the GC to pay you by filing a lien at this time?

a)Yes

b)No

Explanation / Answer

Can you put some pressure on the GC to pay you by filing a lien at this time?

Answer = b)No

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at drjack9650@gmail.com
Chat Now And Get Quote